-
The May 2017 Bond provides $12 million for asbestos remediation.
This is a list of asbestos remediation projects from 2018 to 2023. More schools will continue to receive asbestos remediation work in the coming years through the May 2017 Health Safety and Modernization Bond.
2023 Asbestos Remediation Projects
Astor School
Remove and replace asbestos containing floor tile and mastic in the cafeteria and kitchen areas (4,328 S/F).Beaumont School
Remove and replace asbestos containing flooring in multiple areas of the school (5,056 S/F).Bridger School
Remove and replace asbestos containing flooring (4,075 S/F). Remove and replace asbestos containing pipe insulation (63 fittings). Attic Cleanup (100 S/F) (P&R 10 L/F) Remove wall tiles (870 S/F).Mt Tabor School
Remove and replace asbestos containing flooring (3,280 S/F). Crawlspace Cleanups (5,040 S/F) (P&R 35 L/F). Remove and replace asbestos containing pipe insulation (30 L/F). Remove and replace asbestos containing wall tiles (1,255 S/F).Sellwood School
Remove and replace asbestos containing floor tile and mastic in two classrooms (1,334 S/F). Remove and replace asbestos containing pipe insulation in the cafeteria and kitchen areas (45 L/F).
Woodstock School
Remove and replace asbestos containing floor tile and mastic in the main hallway (2,965 S/F). Clean up approximately crawlspace (5 S/F). Remove and replace interior TSI piping (16 L/F).2022 Asbestos Remediation Projects
2022 Asbestos Remediation Projects
Robert Gray School
Remove asbestos floor tile in the kitchen and various locations. (appx. 1,440 S/F)Robert Gray School
Remove asbestos floor tile in the kitchen and various locations. (appx. 1,440 S/F)Harrison Park School
Remove asbestos flooring in the lobby and main office (appx. 3,600 S/F). Remove ceiling in the office contaminated with asbestos roofing on top (appx. 2,775 S/F). Remove ceiling in cafeteria contaminated with asbestos roofing on top (appx. 4,107 S/F). Remove ceiling sections in lobby contaminated with asbestos roofing on top (appx. 76 S/F). Demo lockers and remove flooring in main hallways (appx. 6,420 S/F). Asbestos roofing remediation in attic (appx. 667 S/F).Martin Luther King Jr. School
Asbestos flooring and wall removal in 2 classrooms, cafeteria area, hall and misc areas (appx 15,650 S/F). Asbestos remediation in crawlspace (appx. 16,250 S/F).Stephenson School
Asbestos flooring removal in 7 classrooms & 3 misc. areas (approx 7,505 S/F).Winterhaven School
Asbestos flooring and wall removal in 4 classrooms, a storage room and a hall (appx 5,750 S/F). Asbestos remediation in crawlspace (appx. 3,275 S/F). Crawlspace cleanup, patch & repair.Woodstock School
Asbestos flooring and wall removal in 4 classrooms, a storage room and the hall (appx. 2,735 S/F). Asbestos remediation in crawlspace (appx. 12,810 S/F). Boiler Room, asbestos duct removal, patch and repair (appx. 200 S/F).Terwilliger School
Asbestos flooring removal in 1 classroom, main hallways & 3 misc. areas (approx 7,505 S/F).
2021 Asbestos Remediation Projects
Robert Gray School
Removal and remediation of pipe insulation in the crawl spaces (approx. 8,000 S/F). Pipe insulation removal & re-insulation in various locations inside the school (approx. 150 L/F). Removal and remediation of pipe insulation and tape in a section of attic (appx. 200 S/F & 20 L/F).Hosford Middle School
Phase 2 - Pipe insulation removal & re-insulation in various locations inside the school (approx. 400 L/F). Removal and remediation of pipe insulation in the crawl space (approx. 3,130 S/F).Jefferson High School
Removal and remediation of pipe insulation a section and tunnel system after a steam leak (appx. 2,300 S/F and 500 L/F).Vernon K-8
Phase 2 - Removal and remediation of pipe insulation a section of crawl space and tunnel system (appx. 6,300 S/F). Removal of pipe insulation and replacement inside 4 tunnel systems (appx. 440 L/F).Winterhaven K-8
Phase 2 - Pipe insulation removal & re-insulation in various locations inside the school (approx. 60 L/F). Removal and remediation of pipe insulation in crawl space (approx. 10,880 S/F).2020 Asbestos Remediation Projects
Beaumont Middle School
Phase 2 - Removal and cleanup of pipe insulation in the crawl space. Removal and replacement of pipe insulation in the basement. Removal and replacement of flooring in various locations.Capitol Hill
Phase 2 - Removal and replacement of flooring in hallway and side rooms.Chapman Elelmentary School
Phase 2 - Removal and replacement of pipe insulation in the basement and fan roomsHosford Middle School
Phase 1 - Removal and cleanup of pipe insulation in the crawl spaces. Removal and replacement of flooring in various locations. Removal and replacement of pipe insulation in fan room.Lane Middle School
Phase 2 - Removal and cleanup of pipe insulation in the portable crawl space.Rigler
Phase 2 - Removal and cleanup of pipe insulation in the portable crawl space. Removal and replacement of flooring in various locations on the main floor.Stephenson
Phase 1 - Removal and cleanup of pipe insulation in the crawl space. Removal and replacement of pipe insulation in the fan room. Removal and replacement of flooring in various locations.Vernon
Phase 1 - Removal and cleanup of pipe insulation two crawl spaces. Removal and replacement of flooring in various locations on the first floor.Vestal K-8
Phase 2 – Repair, removal and cleanup of pipe insulation in the portable crawl space.
Woodstock
Removal and cleanup of pipe insulation in the crawl space. Removal and replacement of flooring in various locations. Removal and replacement of pipe insulation in various occupied locations.2019 Asbestos Remediation Projects
Beaumont Middle School
Asbestos removal and re-insulation of severely damaged piping insulation from basement and portable classroom crawlspaces. Removal of approximately 15,000 square feet of accessible asbestos containing floor tile & mastic from basement, first and second floors and replacement with new non-asbestos flooring.Capitol Hill
Abatement of floor materials. New flooring installed.Jackson Middle School
Asbestos removal and re-insulation of severe to moderately damaged asbestos fireproofing from structural steel decking from; C-Wing basement tunnel entry, Auditorium attic mechanical spaces, D-Wing 1st floor above Library ceiling, and B-Wing above Cafeteria ceiling.Lane Middle School
Abatement of floor materials & pipe insulation in various locations (Tunnel and Crawl Space Included.) New flooring installed.Marysville K-8
Asbestos removal in the crawl space.Rigler Elelmentary
Abatement of floor materials & pipe insulation in various locations (Tunnel and Crawl Space Included.) New flooring installed.Vestal K-8
Abatement of floor materials & pipe insulation in various locations (Tunnel and Crawl Space Included.) New flooring installed.2018 Asbestos Remediation Projects
Tubman Middle School
Removal and of asbestos piping insulation from first and second floors (Above Ceilings). Complete removal of all boiler and piping insulation from the boiler room and selective ceiling removal and replacement throughout building. Removal and replacement of all accessible asbestos containing flooring from first and second floors and the replacement with new non-asbestos flooing.Chapman Elementary School
Removal of approximately 20,000 square feet of accessible asbestos containing floor tile & mastic from basement, first, and second floors and replacement with new non-asbestos flooring.Jefferson High School
Removal of approximately 50,000 square feet of accessible asbestos containing floor tile & mastic from basement, first, second, and third floors and replacement with new non-asbestos flooring.
-
ASBESTOS BAC PROJECT STATUS REPORTS
BAC Health & Safety: Asbestos Status Report November 2023For additional information, visit the following web sites:
½ûÂþÌìÌà Risk Management Asbestos Page
US Environmental Protection Agency
Oregon Department of Environmental Quality
For more information about ½ûÂþÌìÌà Bond asbestos projects please email: schoolmodernization@pps.net